This week saw the completion of the containment systems throughout the facility, which means that all runs to hardware requiring power and/or network connectivity are now complete.
Final backbone basket installed in data hall
Final backbone basket installed in data hall
Containment backbone installed in cold corridor
Containment backbone installed in cold corridor
Cold corridor access control being installed
Cold corridor access control being installed
Access points for future cooling stack controllers installed along cold corridor enclosure
HD CCTV cameras being installed in first floor data hall
HD CCTV cameras being installed in first floor data hall
HD CCTV cameras being installed in first floor data hall
Custom migration flight cases being prepared for specialist hardware during the move into the new facility
Finalisation of cold corridor enclosure sliding doors
Containment bridges being installed for power and network runs to each pod
Containment bridges being installed for power and network runs to each pod
Through-aisle containment bridges fitted with brushes for air management