This week has again seen dramatic progress as we head towards the final stage of the build, largely in the layout of the data hall ready for initial occupation early next year.
First row of cabinets in the first containment pod being bayed together, including the in-line UPS seen towards the middle
First row of first pod bayed together – this view is from inside the cold aisle
A look at the rear of the first row, as baying and levelling is completed
A look at the rear of the first row, with a custom solution for creating a seamless rear door surface despite the UPS being a different depth to the server cabinets
The distribution cabinet being wrapped around one of the facilities structural columns, alongside an empty UPS
Another row coming together
Another row coming together
Another row coming together
The second containment pod nearing completion
A closer look at the customised APC cabinet which encloses the column in this pod