Massive progress has been made over the past few days, with major leaps forward in the cooling system installation which means that technical systems are ready for installation imminently. Great progress has been made in a number of areas throughout the facility, which is always good for seeing the project come together more quickly as we reach the final furlong.
A look across the first data hall after the initial mist coating
Extraction holes prepared for 2N air extraction system
Extraction holes prepared for 2N air extraction system
First air filter delivery on-site
Air filters installed in ceiling grid, for first cold corridor containment pod
Air filters installed in ceiling grid, for second cold corridor containment pod
Office-side structured cabling tied off ready for entry into patching cabinet
The first of an eventual 96 office and supplementary amenity / system ports
‘Tool-free’ termination on our Cat 6 cabling saves lots of time
Flooring in ground floor access corridors reached completion
Installation of our custom tanked floor begins in the cold corridor
Up-stands are installed in cold corridor access doors to allow for floor tanking
Installation of transitional edging is completed
Installation of top edging is completed
Floor covering is laid out in main data hall and provisionally cut to size
Floor covering is laid into corridor ready for gluing and fitting
Floor covering is glued to the subsurface
Flooring is cut to size and fitted to the edging
As is clearly visible, progress has been impressive over the past week, with serious headway made in a number of critical areas.