Structural works are on-going in both data halls this week, including fireproofing and wall extensions. This will lead into the construction of our goods lift shaft, and the installation of our hung ceilings on both levels.
There aren’t a great deal of updates to illustrate with photographs this week, as heavy structural works have meant limited access to certain areas of the building. A large portion of time is also being spent on system design, such as finalisation of the cooling systems both inside the data floors and in supplementary rooms throughout the facility.